News

Works underway at Tronoh Dredgehole

21 February 2025

After extensive planning and scoping, construction is now well underway on Alpine Shire Council's Alpine Better Places Harrietville Project at Tronoh Dredgehole.

Stadelmann Group were awarded the civil works and have almost completed carpark upgrades and path works along Feathertop Track.

Pioneer Park upgrade works and Tronoh car park works are also underway and scheduled to be completed next month.

A broad construction plan and map of the works is outlined below. The plan is subject to change pending weather and other considerations, updates will be provided here and onsite.

If you have any queries about the project, please do not hesitate to contact Council's Project Manager, Gary Noall, on (03) 5755 0555.

Preliminary works program:

  • Jan 17 - Feb 21 - Feathertop Track car park and road works
  • Feb 7 - Feb 28 - Feathertop Track path works
  • Feb 14 - March 14 - Pioneer Park upgrade works
  • Feb 21 - March 30 - Tronoh Car park works